What It Takes to Build a Large Custom Hardscape Project in Arizona

Long gray paver driveway climbing a hillside lot past a boulder retaining wall toward a modern home

Short answer: a large custom hardscape project is several trades sharing one lot. Pavers, walls, gas, power, a pool fence, turf and plants all have to fit together, so the job depends on decisions made before the first shovel: what the lot allows, which approvals you need, where the water will go, what is buried in the yard and what the contract says. If they aren't settled first, finished pavers sometimes have to come back out.

How a Large Project Differs From a Patio Job

A simple patio is usually one crew working with one material for a few days, while a large project changes how the whole job is organized.

  • Many trades on one schedule. A backyard with an outdoor kitchen, a fire feature, lighting and a pool deck needs gas, electrical, masonry and paving done in the right order, and some of it needs inspections in between.
  • The whole lot gets regraded. When most of a yard becomes pavers, turf and walls, rain has nowhere to soak in. The grading plan for the entire property matters more than any single surface.
  • Heavy equipment and haul-off. Old concrete has to be broken up and trucked away, and the base material for a large driveway arrives by the truckload. Gate widths, side yards and the street all affect how the work gets done.

Skid steer with a breaker removing an old concrete driveway, with a dump truck waiting for the debris

Big projects also don't fit the national "value added" figures you may have seen. The 2023 Remodeling Impact Report from the National Association of Realtors estimated that a new paver patio costs about $10,500 and recovers about 95 percent of that at sale, and that an outdoor kitchen costs about $15,000. Those numbers describe an 18 by 16 foot patio and a modest kitchen, averaged across the country, and the report says plainly that it includes no top-of-the-line projects.

Start With What the Lot Allows

Any design has to fit inside what the property allows, and on large Valley lots that means the property lines, the slope and any easements.

Survey, Setbacks and the Title Report

Know where your property lines are before you plan walls or a driveway near them. The City of Scottsdale strongly recommends that any homeowner planning site changes get a boundary survey first, and the same advice holds everywhere. Your title report is worth pulling out too, because easements and deed restrictions show up there and not on the ground.

Hillside Lots

The City of Phoenix requires a hillside review for projects on properties with a 10 percent or greater slope, and that review looks at grading, drainage and how much of the lot is disturbed. A new driveway, a bigger patio or a pool deck on a hillside lot can count against limits that were set when the house was approved, so it is worth asking the city for a hillside determination early.

Belgard's planning guide points out that leveling land can be expensive and suggests building into the slope with terraced walls instead.

Long gray paver driveway on a hillside lot with a stacked boulder retaining wall along one side

Desert Lots and NAOS Easements in Scottsdale

Many North Scottsdale lots carry a Natural Area Open Space (NAOS) easement, land that must stay in its natural desert state. The city's guide says no grading, filling, clearing or excavation of any kind is allowed in the easement, and walls, pools and barbecues can't be built there. The land is still yours, but the easement works like a deed restriction.

The NAOS line usually isn't marked on the ground, which is how people end up planning a patio or a fire pit inside it. The city says the easement should show up in Schedule B of a current title report or on the subdivision plat, and on the city's parcel maps, so check before design starts. A release is sometimes possible if an equal area of natural desert is dedicated somewhere else, and the city asks that it be done before any other plans are submitted.

Desert lots also have protected native plants such as saguaros. If one is in the way, ask about the rules before anyone digs it up, because moving a plant within your yard and hauling it off the property are different questions under Arizona law.

Where the Water Goes

Phoenix replaced the national building code's grading section with its own storm water rules. The City Engineer's 2025 standard says lots must be graded to drain to the front so they don't affect neighbors, that the ground must fall at least 6 inches in the first 10 feet away from the foundation, and that hard surfaces within 10 feet of the house slope at least 2 percent away from it. Where walls or lot lines make that impossible, drains or swales are required.

Monsoon season officially runs from June 15 through September 30, according to the National Weather Service in Phoenix, and a backyard that is mostly pavers and turf has to move a lot of water in a short storm, so the plan should show where every part of the yard drains before any surface goes down.

Approvals: HOA First, Then the City

Most large projects need both an HOA approval and city permits, and one doesn't replace the other.

HOA Architectural Review

If you live in a planned community, the HOA's design committee will want to see the plans. Arizona law, A.R.S. 33-1817, says approval of a construction project's plans "shall not unreasonably be withheld." The same statute doesn't give the HOA a deadline to decide on a backyard project, so submit early and get the approval in writing before any demolition.

Which Pieces Need Permits

Pavers on the ground usually don't need a building permit, but the things around them often do. Here is how the two largest cities handle the common pieces of a big project, based on their own published guides.

Part of the project Phoenix Scottsdale
Garden or seat wall, 3 feet or less No permit No building permit (courtesy site plan review)
Wall or fence over 3 feet Permit Permit
Retaining wall Permit if over 3 feet, or if it supports a house, driveway, pool or fence nearby; over 3 feet needs structural calculations Every retaining wall needs engineered plans
Gas line to a grill, fire pit or fireplace Permit Plumbing permit
New or changed electrical circuit Permit Electrical permit
Patio cover or ramada Permit Permit
Changing an existing pool fence New barrier permit Pool barrier rules apply

Scottsdale exempts masonry outdoor fireplaces, fire pits and barbecues from a building permit, but the gas line that feeds them still needs its plumbing permit. Scottsdale also exempts low-voltage landscape lighting and patios or drives that sit no more than 30 inches above grade. In Phoenix, a driveway that crosses the right-of-way to the street has its own rules, and pavers in a long apron can require a maintenance agreement with the Street Transportation Department. Other Valley cities have their own versions of these rules, so check yours.

Retaining Walls and Seat Walls

In Phoenix, a short retaining wall still needs a permit if it holds back a load such as a driveway, a pool or a house, or if a fence sits on it or within 3 feet of its uphill side. Scottsdale requires engineered plans for every retaining wall, whatever the height. Seat walls around a fire pit or patio are usually short garden walls, which is why they rarely need a permit. Our block walls and masonry page covers wall types in more detail.

Natural stone garden wall running beside a curved paver path with desert shrubs

If the Project Touches the Pool Fence

Arizona law requires a pool barrier at least 5 feet high, with no opening a 4-inch sphere can pass through and self-closing, self-latching gates that open away from the pool, with the latch at least 54 inches above the ground. Phoenix goes further for remodels: its pool barrier guide says a new permit is required to enlarge, alter, repair, remove, convert or replace an existing approved barrier, and any change to an existing enclosure has to meet the current standard. Temporary fences and alarms don't count as the barrier.

So if a backyard renovation moves the pool fence, adds a gate, or replaces a back door that forms part of the barrier, that piece needs its own barrier permit in Phoenix and should be in the plan from the start.

What Goes in the Ground Before Anything You Can See

Arizona 811 and Private Lines

Arizona law requires anyone who digs to contact Arizona 811 at least two full working days ahead, and the service is free. Utilities must mark their lines within two working days, and the marks are good for 15 working days, under A.R.S. 40-360.22. Utilities mark only what they own, which typically stops at the meter. Lines past the meter belong to you, and a private locating service may be needed to find them before a large excavation.

Gas and Power for Kitchens, Fire Features and Lighting

An outdoor kitchen, a gas fire feature or new circuits for lighting all need permits in both Phoenix and Scottsdale, and outdoor outlets at a home need ground-fault protection under the electrical code. Any pipe or wire that will run under pavers or turf has to be in the ground before the paving goes down. Running empty sleeves under a driveway or patio for future lines is far cheaper than cutting pavers out later. If a kitchen is part of the plan, our outdoor kitchen planning guide covers the grill clearances and propane rules that shape the island.

Base Depth for Driveways and Patios

Driveways need a deeper base than patios. Guidance from the Interlocking Concrete Pavement Institute, now part of the Concrete Masonry and Hardscapes Association, calls for 4 to 6 inches of compacted aggregate base under walkways and 6 to 8 inches under residential driveways, and more where the soil calls for it. It recommends pavers about 2 3/8 inches (60 mm) thick for driveways and herringbone patterns where cars drive regularly. Belgard's installation guide also calls for a slope of at least 1.5 percent away from the house. Our guide to the best driveway material for Phoenix and our paver driveways page go further into driveway choices.

Circular paver driveway in front of a ranch home

Stone Veneer and Clearances

Stacked stone on columns, walls, kitchens and fireplaces has installation rules of its own. The industry installation guide for adhered manufactured stone veneer (written for compliance with ASTM C1780) calls for 2 inches of clearance from soil or 1/2 inch from a paved surface where the backing is concrete or masonry, and warns against constant water from sprinklers, pools or downspouts. Stucco walls have a weep screed that must stay at least 4 inches above soil or 2 inches above paving, which limits how high a new patio or pool deck can sit against the house. Our stone veneer page shows more of this work.

Exterior wall clad in multicolor stacked stone veneer under a tile roof

The Order of Work on a Big Job

Large hardscape jobs usually follow this sequence, because each step depends on the one before it.

  1. Survey, title check and design. Property lines, easements, slope and drainage set the limits.
  2. HOA approval and city permits. Get both in writing before anything is torn out.
  3. Arizona 811 and private line locates. Mark everything before digging.
  4. Demolition and haul-off. Old concrete, turf and rock come out.
  5. Rough grading and drainage. The lot is shaped so water runs where the plan says.
  6. Underground work. Gas, electrical, irrigation and empty sleeves go in, with inspections where required.
  7. Walls, footings and structures. Retaining walls, seat walls, kitchen islands, fireplaces and pergola footings.
  8. Base and flatwork. Compacted base, then pavers, porcelain or travertine.
  9. Veneer and finishes. Stone veneer, countertops and caps.
  10. Turf, plants and lighting. The soft surfaces and the lights go in last, so heavy work doesn't damage them.

Weather affects the schedule too. Summer crews start very early to avoid the worst heat, and monsoon storms can stop work for a day or flood an open excavation, so a large project that starts in spring should plan around both.

Hiring for a Large Project

Arizona law gives homeowners several protections on a large job, and most of them depend on hiring a licensed contractor and having a complete written contract.

Check the License Yourself

Arizona's handyman exemption covers only small jobs: the total contract price must be under $1,000, and the exemption doesn't apply at all if the work needs a building permit (A.R.S. 32-1121). Any large hardscape project needs a contractor licensed by the Arizona Registrar of Contractors. You can look up any license at roc.az.gov or by calling 1-877-692-9762, and the Arizona Attorney General recommends checking before you sign. Agave Landscape's license number is ROC 321033.

What the Contract Has to Say

For residential work over $1,000, A.R.S. 32-1158 lists what the written contract must include. Use it as your checklist when comparing bids:

  • The contractor's name, business address and license number
  • Your name, mailing address and the job address
  • The date of the contract and the estimated completion date
  • A description of the work and the total price
  • The amount of any deposit
  • Each progress payment and the stage of construction when it is due
  • A signed statement that you can file a written complaint with the Registrar, with its phone number and website

The contractor must also give you a copy of every signed document and a signed receipt for any cash.

Deposits, Progress Payments and Lien Waivers

On a big job you may receive "preliminary 20-day notices" from suppliers and subcontractors you have never met. Arizona law requires them (A.R.S. 33-992.01), and the notice itself says it is not a lien and is not a reflection on anyone's integrity. It exists so you know who has worked on or supplied your project. For an owner-occupied home, A.R.S. 33-1002 allows a lien only by someone who signed a written contract directly with the owner. Even so, it is good practice to ask for lien waivers with each progress payment, which the 20-day notice itself suggests. This is general information, not legal advice.

Product Warranty Versus Workmanship Warranty

Belgard backs its pavers with a lifetime transferable limited warranty for residential use, but it is valid only when the pavers are installed to Belgard's or the CMHA's guidelines, and it doesn't cover replacement labor. The workmanship warranty, which covers the installation itself, comes from the contractor. Ask for both in writing.

What the Recovery Fund Covers

Arizona's Residential Contractors' Recovery Fund can pay up to $30,000 per claimant when a licensed contractor fails to complete a job or does defective work (A.R.S. 32-1132.01). To qualify, the home must be your primary residence and the contractor must have been properly licensed. Homes held in a limited liability company or a revocable living trust can also qualify under conditions the statute spells out. Second homes don't qualify, and hiring an unlicensed crew forfeits the protection completely.

Questions to Ask Before You Sign

  • Who will be on site every day, and who do I call with a question?
  • Which parts of the work are done by your own crews, and which are subcontracted?
  • Who handles the HOA submittal and the city permits?
  • How are changes priced once the work starts?
  • How will the yard drain, and where will sleeves and lines run under the paving?

Our project gallery shows large projects we've built, including porcelain pool decks, travertine, artificial turf, pergolas, outdoor lighting and full landscape design.

Frequently Asked Questions

How Long Does a Full Backyard Renovation Take?

It depends more on approvals and the number of trades than on the size of the yard. HOA review and city permits can take longer than the construction itself, and work with inspections, such as gas lines, electrical and pool barriers, has to wait for each inspection before the next step. Ask any contractor for an estimated completion date in writing, which Arizona law requires in the contract.

Do I Need a Permit for a Retaining Wall in Phoenix or Scottsdale?

Often, yes. In Phoenix, a retaining wall over 3 feet needs a permit and structural calculations, and a shorter wall still needs a permit if it supports a load such as a driveway, pool, house or fence. Scottsdale requires engineered plans for every retaining wall, whatever the height. Garden and seat walls 3 feet or shorter usually don't need a building permit in either city.

Do I Need a Permit to Move My Pool Fence During a Backyard Remodel?

In Phoenix, yes. The city's pool barrier guide says a new permit is required to enlarge, alter, repair, remove, convert or replace an existing approved barrier, and the changed work must meet the current standard: a 5-foot barrier with self-closing, self-latching gates and the latch at least 54 inches high. A back door that is part of the barrier counts too.

How Do I Check If a Contractor Is Licensed in Arizona?

Look up the contractor's license on the Arizona Registrar of Contractors website, roc.az.gov, or call 1-877-692-9762. Check that the license is active and in the company's name. Any job of $1,000 or more, or any job that needs a building permit, requires a licensed contractor, and hiring one is also what keeps you eligible for Arizona's Residential Contractors' Recovery Fund.

Can a Subcontractor Put a Lien on My House in Arizona?

For an owner-occupied home, Arizona law allows a lien only by someone who signed a written contract directly with the owner. You may still receive preliminary 20-day notices from suppliers and subcontractors, which the law requires and which state that they are not liens. Asking your contractor for lien waivers with each progress payment is a sensible extra step. This is general information, not legal advice.

Does My HOA Have to Approve My Backyard Remodel?

If your community documents require architectural approval, yes, and it is separate from any city permit. Arizona law says the HOA can't unreasonably withhold approval of a project's plans, but it sets no deadline for the HOA to decide on a backyard project. Submit the plans early, include the materials and colors, and get the approval in writing before demolition starts.

Can I Build a Large Backyard Project in Phases?

Yes. Design the whole yard first, so the grading, drainage and underground lines for later phases go in during the first one. Running sleeves under the first pavers for a future kitchen, fire feature or lighting saves cutting them out later. Tell your contractor about every future phase at the start.

When Is the Best Time to Start a Big Backyard Project in Phoenix?

Many homeowners start planning in winter or early spring, because approvals take time and the work then runs before the worst heat. Monsoon season officially runs from June 15 through September 30, and storms can pause work or flood open excavations. Summer projects still get built every year, with crews starting very early in the day.